Annexure-1.C
STATUS OF CONSTRUCTION OF MDSD CENTRES IN ASSAM
Sl | Name of the Centres | Location | District | Status |
1 | MDSD Temporary Centre | Banderdewa | Lakhimpur | Completed |
2 | MDSD Temporary Centre | Margherita | Tinsukia | Completed |
3 | MDSD Temporary Centre | Mangoldoi | Darrang | Completed |
4 | MDSD Temporary Centre | Bongaigaon | Bongaigaon | Completed |
5 | MDSD Temporary Centre | Gauripur | Dhubri | Completed |
6 | MDSD Temporary Centre | Chaygaon | Kamrup | Completed |
7 | MDSD Temporary Centre | Silchar | Cachar | Completed |
8 | MDSD Temporary Centre | Rangia | Kamrup | Completed |
9 | MDSD Permanent Centre | Badarpur ghat | Karimganj | Completed |
10 | MDSD Permanent Centre | Margherita | Tinsukia | Completed |
11 | MDSD Permanent Centre | Samoguri | Nagaon | Completed |
12 | MDSD Permanent Centre | Chapor | Dhubri | Completed |
13 | MDSD Permanent Centre | Ouphulia (Tingkhong Block) | Dibrugarh | 40% completed |
14 | MDSD Permanent Centre | Titabor | Jorhat | 90% completed |
15 | MDSD Permanent Centre | Podumoni | Golaghat | 90 % completed |
16 | MDSD Permanent Centre | Mukalmuwa | Nalbari | 90% completed |
17 | MDSD Permanent Centre | Dhekiajuli | Sonitpur | 60% completed |
18 | MDSD Permanent Centre | Bihpuria | Lakhimpur | 90% completed |
19 | MDSD Permanent Centre | Goalpara | Goalpara | 30% completed |
20 | MDSD Permanent Centre | Sisiborgaon Block | Dhemaji | 90% completed |
21 | MDSD Permanent Centre | Mautgaon | Sivasagar | 40% completed |
22 | MDSD Permanent Centre | Chapakhowa | Tinsukia | 70% completed |